Project Profile

 

Project: Black Liquor Treatment Facility

Location: Australia

Project Scope: INGENII performed all structural engineering for the design of the steel framing of this black liquor process addition to an existing paper mill. INGENII was responsible for the structural design of three process towers supporting: three vertical heaters, a surface condenser and a 75,000 kilogram vapor body. Design criteria included allowance for an identical future process tower. Steel weight for the three units totaled over 48 metric tons (54 tons US). All engineering was performed according to local Australian design standards using locally available steel shapes.